Executive Order
National Emergency on the Bulk-Power System
Executive Order 14421 — Declaring a National Emergency To Secure the United States Bulk-Power System, signed August 26, 2026
Sources: govinfo.gov · federalregister.gov
Dateline: Washington, D.C.
Status: Signed by President Trump on August 26, 2026; published in the Federal Register on August 31, 2026 (91 FR 55995).
Type: Executive order
Item date: 2026-08-26 (signed)
Identifier: Executive Order 14421; Federal Register document 2026-17843; 91 FR 55995
Source: Official PDF
Key points
- Executive Order 14421, signed by President Trump on August 26, 2026, declares a national emergency with respect to the foreign supply of bulk-power system electric equipment, using IEEPA and the National Emergencies Act.
- Sec. 2: prohibits acquisition, importation, transfer or installation of foreign-produced bulk-power system electric equipment in covered transactions after the order date, where the Secretary of Energy finds equipment from a Covered Foreign Entity poses an undue risk. The Secretary may impose conditions on equipment already installed.
- Sec. 3: the Secretary must publish implementing rules within 120 days and identify equipment posing unacceptable risk. Sec. 4: within 180 days the Secretary must recommend Federal Acquisition Regulation revisions.
- Sec. 5 defines the bulk-power system to include transmission lines rated at 69 kV or more, but not local distribution. Sec. 6 requires reports to Congress.
- Sec. 7: the order creates no right or benefit enforceable by any party.
What it means for everyday Americans
The text does not state a direct effect on individuals. It restricts certain transactions in foreign-produced grid equipment by persons subject to U.S. jurisdiction, directs rulemaking and procurement recommendations, and says it creates no enforceable right or benefit.
Votes
This is an executive order, not a legislative vote.
Short summary
Executive Order 14421, “Declaring a National Emergency To Secure the United States Bulk-Power System,” was signed by President Trump on August 26, 2026, and published in the Federal Register on August 31, 2026 (91 FR 55995). Under the International Emergency Economic Powers Act and the National Emergencies Act, it declares a national emergency over the foreign supply of bulk-power system electric equipment.
Section 1 states that foreign actors are increasingly creating and exploiting vulnerabilities in the bulk-power system and that equipment might contain digital backdoors allowing remote access. Section 2 prohibits, for transactions begun after the order date, any acquisition, importation, transfer or installation of foreign-produced bulk-power system electric equipment where a foreign country or its national has an interest and where the Secretary of Energy determines that the transaction involves equipment from a Covered Foreign Entity and poses an undue risk of sabotage, subversion or supply disruption. The Secretary may also impose conditions on equipment already installed, after weighing reliability and safety, and may set up criteria for pre-qualified equipment and vendors.
Section 3 gives the Secretary implementing authority and requires rules within 120 days. Section 4 requires the Secretary, within 180 days, to recommend changes to the Federal Acquisition Regulation to consider national security risks and favor United States-made energy infrastructure. Section 5 supplies definitions, including that the bulk-power system includes lines rated at 69 kV or more. Section 6 requires reports to Congress, and Section 7 says the order creates no enforceable right or benefit.
Long summary
Order and date. Executive Order 14421 of August 26, 2026, signed by President Trump, published at 91 FR 55995 on August 31, 2026 (Federal Register document 2026-17843). It relies on the International Emergency Economic Powers Act (IEEPA), the National Emergencies Act and section 301 of title 3, United States Code.
Section 1. National Emergency. The order says the bulk-power system supplies electricity for national defense, emergency services, critical infrastructure and the economy, that foreign actors increasingly create and exploit vulnerabilities in it, and that growth in advanced manufacturing, data centers, artificial intelligence and defense production has increased dependence on reliable electricity. It states that foreign-produced equipment may have digital backdoors and that reliance on foreign sources creates a supply chain vulnerability. The President finds an unusual and extraordinary threat and declares a national emergency.
Section 2. Prohibitions and Implementation. Subsection (a) prohibits any acquisition, importation, transfer or installation of foreign-produced bulk-power system electric equipment by a person subject to U.S. jurisdiction, where a foreign country or national has an interest, the transaction began after the order date, and the Secretary of Energy, in coordination with the Director of the Office of Management and Budget and in consultation with the Secretary of War, the Secretary of Commerce, the Secretary of Homeland Security and the Director of National Intelligence, has determined that the equipment comes from a Covered Foreign Entity and the transaction poses an undue risk of sabotage, subversion, unauthorized access, malicious remote action, supply disruption or catastrophic effects, or otherwise an unacceptable national security risk. Subsection (b) lets the Secretary impose conditions on equipment already installed, including identifying, isolating, monitoring, securing, disconnecting, replacing or removing it, after considering reliability, safety, availability of replacements and continuity of service, with phased compliance. Subsections (c) through (f) allow mitigation measures as a precondition for approval, state that the prohibitions apply notwithstanding earlier contracts or licenses, allow criteria and a published list of pre-qualified equipment and vendors, and prohibit evasion and conspiracy.
Section 3. Authorities. The Secretary may direct the timing of ceasing transactions, order replacement of equipment, adopt rules and use IEEPA powers; each agency head must take appropriate measures. Rules may designate Covered Foreign Entities and set licensing procedures, and must be published within 120 days. The Secretary must identify risky equipment and recommend ways to inventory, isolate, monitor or replace it.
Section 4. Federal Energy Infrastructure Procurement. Within 180 days the Secretary, with the FAR Council, must recommend revisions to the Federal Acquisition Regulation, and the FAR Council must consider proposing amendments within 90 days after receiving them.
Sections 5 to 7. Section 5 defines terms, including “bulk-power system,” “bulk-power system electric equipment,” “foreign-produced” and “Covered Foreign Entity.” Section 6 directs recurring and final reports to Congress. Section 7 states the order is implemented consistent with law and appropriations and creates no enforceable right or benefit.
Sources
- Executive Order 14421, signed August 26, 2026, Federal Register. Official PDF
- Executive Order 14421, official text page. Official text